Field report: production-house intranet
Delivery of a corporate intranet joining client relationship records, production administration and departmental reporting for a film and television production house.
May 2003 — Engagement
A North American production house appointed HAWD to provide a common internal system for its commercial, production and facilities teams. The company produced television advertising, commissioned programmes and corporate films across two sites. Its staff included permanent producers and editors, with freelance crews and specialist contractors engaged against individual productions.
This was HAWD’s first major corporate engagement. Previous commissions had principally involved public websites and smaller internal applications. Martin Half led the proposal and contract discussions, with two developers assigned to implementation and a separate allowance for on-site commissioning.
The client had recently introduced Microsoft Business Solutions CRM for its sales and account-management staff. Production administration remained on a custom Perl application developed in house over several years. The two systems held overlapping client and job information, while departments maintained additional spreadsheets and printed schedules. The brief was to provide a single place to find current information and reduce repeated entry between departments.
Discovery and specification
HAWD held workshops with producers, accounts, studio management, equipment stores and the tape library. The agreed intranet included staff notices, a directory, production summaries, budget approvals, room and equipment availability, document links and departmental work lists. Microsoft CRM would remain the commercial record, while the Perl application would continue to maintain production resources and operational history.
The integration design provided an association between each CRM opportunity and its production number. Approved commercial changes would be passed to the production application through a scheduled exchange service. The intranet would display the resulting status and provide an audit history showing who had submitted and approved each change.
Accounts required summaries of committed expenditure and completed work. Producers required a current view of bookings and delivery dates. Facilities staff requested consolidated work lists that could be printed for the following shift. Library staff required links from a production to its registered media and storage locations.
The client approved a departmental permission model and nominated one person from each team to review the interface. The project included migration of the active job register, operating documentation, backup and restore procedures, and training for administrators and ordinary users.
Implementation
The intranet was implemented on Windows 2000 Server and IIS, with SQL Server 2000 holding its reporting tables and integration history. HAWD added exchange routines around the existing Perl system and retained its established production screens for specialist operations. Staff accessed the new pages through Internet Explorer on the office network.
Development proceeded against copies of the client’s records. The first interface review resulted in shorter approval forms, production numbers displayed beside client names and separate lists for current work and completed productions. HAWD also added a printable exception report for records that could not be associated automatically.
The exchange service was tested with new jobs, budget revisions, booking changes and completed work. Departmental users checked the resulting screens and printed reports against the source records. The client’s administrator restored the intranet database to a spare machine and verified access to the associated documents.
26 September — Commissioning
HAWD attended both sites for migration and training. The active production register was reconciled with the commercial records, and the department representatives reviewed their outstanding work. Producers completed supervised approvals, accounts checked the totals and facilities staff printed the next shift’s schedules.
The client signed off the intranet after the acceptance session. HAWD supplied the installation record, account permissions, scheduled-task list and support contact details. The agreed opening balance and job register were retained with the commissioning documents.
The corporate intranet entered service on 26 September 2003. Microsoft CRM and the in-house Perl application were connected through the exchange service, departmental checks were completed and the client accepted the installation following staff training.
30 September, 07:15 — Stores enquiry
The equipment manager called a producer to ask whether a location shoot had been cancelled. A collection vehicle had arrived for its lighting package, although the crew was still expecting to use it that morning. The producer checked the intranet and found the production marked complete.
Similar enquiries followed from another studio and an editing suite. Overnight work lists had instructed departments to release resources against eleven active productions. Freelancers had received cancellation messages, equipment collections had been booked and rooms had been returned to the availability list. The intranet showed the actions as processed.
The production manager asked staff to stop further collections and contacted HAWD. By that point, the first equipment vehicle had left and a second had been loaded. A studio released by the overnight process had also been booked to another production, whose scenery was being moved into the loading area.
Studio B
The outgoing production had prepared an indoor rain sequence. Its overnight release sheet included the hired drainage pumps, temporary hoses and catchment sections used around the set. The stores crew collected these with the rest of the listed equipment and signed the resources back to the supplier.
The incoming production’s scenery then occupied the service passage, restricting access to the studio floor. Meanwhile, the special-effects subcontractor arrived with the previous afternoon’s printed call sheet. Its crew had not received the cancellation messages sent to the production’s individual booking contacts. They began the scheduled rain-system test from the control position above the set.
Water reached the floor without the temporary drainage arrangement in place. Staff attempting to reach the floor-level isolation point found the passage obstructed by the newly delivered scenery. The effects operator stopped the supply from the control position after receiving a radio call, but water had already passed through the studio doors and entered the goods-lift shaft.
The lift carried the first trolley of incoming scenery down to the basement while water was entering the shaft. It stopped between floors, leaving the trolley and its load inaccessible. Water continued into the basement corridor, where the tape library and central machine room were located. An electrical fault then interrupted power to the editing suites and the remaining studio communications equipment.
The building was evacuated. Emergency attendance was followed by isolation of the affected electrical supply and pumping out of the basement. HAWD’s engineers arrived while staff were attempting to establish which productions were still on site and which equipment had already been collected.
Operational recovery
The equipment suppliers had allocated several returned items to other customers. Replacement hire was available only in part, and two crews could not be reassembled within the booked location periods. The incoming production could not proceed because its scenery remained in the lift and the studio supply was isolated.
Editors reported that shared storage was unavailable. Water had reached disk shelves, tape equipment and the cabinets holding production masters. The tape library began separating affected media under specialist supervision. Finished client materials, source recordings and work in progress were all represented in the damaged areas.
HAWD disabled the exchange service and restored the intranet database to a separate machine. This recovered the application records but did not reverse the cancellations, retrieve the hired equipment or restore the production media. The job register could again show a studio booking that the building could no longer accommodate.
Integration review
The first incorrect transition followed a producer’s approval of a revised budget on 29 September. HAWD’s exchange code represented approval as a release of the job for production. The existing Perl routine receiving that value used release to mean that the job’s allocated resources were no longer required.
A second error widened the update. The exchange selected records using the client account identifier where the production application expected an individual job number. All eleven active productions under that account were passed through the same resource-release routine.
The downstream instructions were then generated by the production application’s normal closure process. Its room schedules, supplier returns and cancellation messages agreed with the state it had been given. The intranet treated successful delivery of those instructions as confirmation that the exchange had completed.
The acceptance fixtures contained one active production for each test account. The review also found that the budget-approval and resource-return tests had been checked separately. The records did not contain a test that followed a budget approval through the overnight operational work lists for a client with several active productions.
The effects subcontractor was held against a company-level purchase order rather than the individual crew register. Its instructions therefore continued to refer to the previous call sheet after the other bookings had been cancelled. This difference accounted for the rain test proceeding after the drainage equipment had been returned.
October–November — Commercial position
The basement electrical installation and machine room remained unavailable while repairs and assessment continued. The production house hired external editing capacity, but several projects lacked recoverable source material. Specialist media recovery returned some recordings; it did not provide a complete set for the eleven affected productions or the older work stored alongside them.
Clients withheld milestone payments and submitted claims for replacement production, missed delivery dates and loss of supplied materials. Two advertising campaigns lost their scheduled transmission windows. The cost of hiring alternative facilities and assembling replacement crews exceeded the receipts from the remaining work.
The lender withdrew the company’s operating facility after reviewing the revised cash position. Supplier accounts moved to payment in advance, and the production house was unable to fund the next payroll or continue the recovery programme. It ceased trading on 14 November and entered bankruptcy proceedings. Most staff were dismissed, with a small records team retained for the insolvency process.
The appointed insolvency representatives notified HAWD of a claim covering the integration failure and the resulting business losses. The claim included the sequence of cancellations, removal of equipment, studio flooding, media damage and interruption of production.
Indemnity notification
HAWD submitted the claim to its professional indemnity insurer with the contract, specification, commissioning record and integration review. The insurer requested the original proposal form and the correspondence in which HAWD had agreed to connect the production processes.
The insurer subsequently declined cover. Its position was that the declared business comprised website design and maintenance, while the disputed engagement included operational production-system integration outside the insured description. It also relied on the contractual responsibility HAWD had accepted for consequential losses. The refusal covered both payment of the client’s claim and funding of HAWD’s defence.
HAWD disputed the insurer’s interpretation and referred the placement correspondence back to its broker. The client’s claim remained active while those discussions proceeded. No payment or defence appointment was made by the insurer.
12 December — Legal instruction
Martin Half instructed HAWD’s first solicitor specialising in professional indemnity disputes. The initial retainer covered the response to the production house’s claim, review of the insurer’s refusal and preservation of the project records. HAWD was required to fund the opening work itself.
The solicitor requested the complete source history, acceptance evidence, insurance proposal and all correspondence with the client following the incident. Further communications concerning liability were referred through the solicitor. HAWD’s final project invoice remained unpaid.
The client has ceased trading and entered bankruptcy proceedings. Its claim against HAWD remains unresolved. HAWD’s indemnity insurer has refused cover, and the company has instructed its first specialist indemnity solicitor at its own expense.