Field report: port shipping-status integration
Design and integration of a shared container-status service for a network of six commercial ports, providing consistent movement records to terminal operators, shipping lines and freight customers.
January 2019 — Discovery and specification
The client operated container terminals at six ports, with separate terminal operating systems and a mixture of carrier portals, scheduled file transfers and manual status reporting. A container could be recorded as discharged in a terminal ledger while the shipping line’s portal continued to show it aboard. Customer-service staff reconciled these differences by telephone and circulated corrected spreadsheets at the end of each shift.
HAWD was commissioned to provide a common status layer. The specification covered vessel calls, container identifiers, gate movements, discharge and loading confirmations, customs holds and availability for collection. It included a staff dashboard, carrier integrations and a customer-facing tracking interface. Crane operation, loading instructions and other equipment-control functions were outside the commissioned scope.
Discovery workshops brought together terminal operations, shipping-line account teams, port IT and the group’s customer-service department. The resulting event catalogue distinguished physical movement from administrative release, recorded the source and time of each update, and allowed staff to inspect the history behind the current displayed status. Local timestamps were retained alongside a common reporting time.
February — Carrier portals and data mapping
The integration team built adapters for the operators’ existing exports and the interfaces made available by participating carriers. Container numbers, voyage references and terminal codes were normalised into a shared record. Differences between a carrier’s booking reference and the terminal’s work reference were represented explicitly, allowing a customer enquiry to be traced without asking the terminal to adopt the carrier’s internal numbering.
The portal showed the latest confirmed event, its location and its age. Staff could distinguish a delayed source update from a container awaiting clearance, and disputed events could be referred to the relevant terminal with the supporting history attached. Carrier users were restricted to their own consignments. The internal view supported searches by vessel call, container number and collection reference, with exports for shift handover.
Integration testing used recent calls from each port, including transhipments, cancelled collections and containers moved between storage areas. The carrier teams checked the resulting sequences against their own records. Differences in the meaning of “available” were resolved in the interface wording rather than collapsed into a single status.
March — User testing and terminal integration
Dispatch staff, terminal supervisors and customer-service agents completed a series of timed tasks using the proposed interface. These included locating an overdue consignment, explaining a customs hold and identifying which terminal should answer a movement query. The first round resulted in larger timestamps, a clearer distinction between vessel and container status, and a printable history that retained the source-system references.
During onsite integration at the largest port, the HAWD engineer investigated a delay between a crane completing a movement and the event appearing in the terminal’s scheduled export. A diagnostic capture showed movement messages travelling in clear text on an inadequately segregated network. The messages included the container reference, working location and completion status needed by the new service.
The engineer identified a maintenance interface on the crane and loading-control gateway and implemented a direct connection to obtain those updates. The local installation record described this as an alternative movement source. The connector supplied events to the existing status pipeline, reducing the observed delay from several minutes to a few seconds. The port’s operations team requested the same display behaviour for its other active berths.
The revised source mapping was incorporated into the rollout package. HAWD’s project record credited the onsite integration with improving the timeliness of loading confirmations without requiring replacement of the terminal systems. Other ports received the common portal and their respective source adapters; the direct gateway connection was installed at the largest terminal.
26 March — Acceptance and handover
Acceptance took place with representatives of all six port operators and the participating carrier teams. Staff followed selected containers from gate receipt through storage, vessel loading and departure, checking the displayed events against terminal records and shift reports. The revised interface passed the agreed task-based usability checks, and carrier permissions were verified using separate test accounts.
The production service was deployed with monitored application servers, scheduled database backups and documented configuration. A restoration exercise recovered the portal and its event history onto a replacement application host. Terminal staff received training in exception handling, source-status checks and escalation to HAWD. The operators signed the acceptance record and transferred routine use to their shift teams.
The six-port status service and carrier integrations passed acceptance on 26 March 2019. The operators approved the interface, received training and took the system into production.
8 May, 08:14 — Loading-status discrepancies
After six weeks of operation, the largest terminal reported that the portal was repeating loading confirmations for a vessel alongside at its principal container berth. A supervisor could see fresh timestamps against a working location that had already been reported complete. The carrier portal continued to advance the loaded-container total, while the terminal’s planning view showed several tasks awaiting reconciliation.
The local IT team checked the status connector and found an increasing retry count. Its connection remained established and the application health check was passing. At 08:22, HAWD support joined a remote session and began comparing the incoming movement records with the portal’s event history. The immediate support ticket concerned duplicate updates and an inaccurate progress total.
During the same period, the terminal’s loading system continued allocating work to cranes serving the vessel’s starboard side. The vessel’s loading officer queried the distribution with the terminal. The planning display still showed the intended sequence, and the terminal team initially treated the disagreement as part of the status-reporting problem already under investigation.
08:46 — Berth operations
The vessel developed a visible list. The loading officer requested suspension of work and a reconciliation of the containers already placed aboard. Crane operators reported that completed moves were being followed by further assignments to the same working area. Terminal supervisors began stopping the affected equipment locally while attempting to establish which instructions remained active.
At 08:53, HAWD stopped the portal’s carrier-update workers to prevent further publication of the disputed totals. The site connector ran as a separate service and remained connected to the port gateway. Operators reported continuing task allocations, and the terminal’s control-system supplier was called into the incident.
Port staff applied the emergency stops, and loading was stopped at the berth at 09:01. By that point, the actual distribution of containers differed materially from the approved loading plan. The vessel remained heavily listed to starboard. Shore personnel cleared the immediate quay area and the harbour authority requested tug assistance.
09:09 — Vessel movement and collision
Quayside footage recorded the failure of successive mooring lines as the vessel moved away from the berth. Remaining restraints did not hold it alongside. The ship entered the approach channel while an inbound container vessel was making its final approach under pilotage.
Berth staff and the terminal control room concentrated on the vessel breaking free, clearing personnel from the mooring area and warning traffic in the approach channel. The crane operation had been stopped, and the supervisors who had been coordinating that intervention were now assisting the harbour authority with the developing collision.
The harbour authority instructed the incoming vessel to abort its approach. The available distance was insufficient to prevent contact. The bow of the listed ship struck the incoming vessel, after which the listed ship continued to heel and capsized within the port. The hull and displaced containers obstructed the principal access channel and the adjacent turning area.
During this response, two of the loading cranes resumed their automated cycles. With the vessel no longer alongside, they carried containers out over the vacant berth, lowered them to the recorded placement positions and released them into the water. The cranes then returned to collect further containers from the landside transfer area. Several cycles were completed while port staff were occupied with the collision and the vessel in the channel.
A quay worker reported the continuing releases to the control room. Port engineers isolated the affected crane supplies and confirmed that movement had ceased. The additional containers obstructed the water immediately below the berth and were added to the emergency survey area.
Port emergency services, rescue crews and the coastguard attended. Crew recovery and clearance of the water took priority over inspection of the berth systems. The incoming vessel was secured for damage assessment. All commercial movements through the affected entrance were suspended.
The capsized vessel was carrying cargo with an aggregate declared value of approximately £500 million. That figure excluded the value of either vessel, damage to port infrastructure, salvage costs and losses arising from interruption of terminal operations.
May — Records preserved for investigation
HAWD engineers attended the port with the terminal-system supplier after access to the relevant offices was restored. Images were taken of the connector host and application servers, and the operators preserved gateway records, crane task journals, loading plans and available network captures. The HAWD connection was isolated. The remaining ports continued to receive status information from their scheduled interfaces while the group reviewed the deployment.
The first reconstruction established that the portal’s repeated events and the crane task allocations were temporally related. They did not, by themselves, establish which system had originated the repeated work. Investigators aligned the independent clocks and compared the sequence against quayside footage and the vessel’s recorded loading observations.
The direct gateway connection had been implemented as a two-way session. Its recovery routine could transmit a stored movement message back to the gateway when confirmation was not received. This behaviour had not formed part of the original status-service specification. The gateway supplier identified the receiving component as a shared handler used for both movement records and requests to allocate loading work.
June — Proposed failure sequence
The joint technical working group developed a reconstruction in which a single dropped acknowledgement packet initiated the event. The gateway-side capture contained the acknowledgement; the connector-side capture did not. The HAWD connector consequently treated the exchange as incomplete and replayed its stored instruction.
Under the reconstruction, the port gateway interpreted the replay as a fresh loading instruction rather than a request to confirm a previous movement. The terminal scheduler then selected another eligible container for the specified working location. Subsequent completion messages described a state different from the one expected by the HAWD reconciliation routine, which attempted to correct the discrepancy by transmitting again.
The correction cycle continued. Each newly allocated task received a new terminal work reference, so the resulting crane jobs were not rejected as duplicates of an existing job. Work accumulated on the starboard side, while the planning interface continued to present the distribution derived from the approved loading plan. The portal’s event history recorded the completed moves without reflecting their effect on vessel stability.
The task journals also contained allocations issued after the emergency-stop entries, including the movements that released containers into the vacant berth. The terminal retained the vessel’s last working position throughout that period. The record confirmed that crane operation had resumed, but did not establish how the emergency-stop condition had ceased to inhibit movement. That question remained under separate examination by the control-system supplier and the investigators.
A bench reconstruction using the recovered connector and a supplier-provided gateway environment reproduced the sequence from a withheld acknowledgement to repeated work allocation. It did not reproduce the vessel’s physical behaviour. Marine investigators separately assessed the actual loading distribution, stability, mooring failure and collision. The technical working group described the packet-loss sequence as its leading explanation; HAWD did not accept it as an agreed finding of liability.
June–November — Recovery and port access
The salvage programme required surveys of the submerged hull, removal of accessible containers and those released into the vacant berth, pollution controls and clearance of cargo from the channel. Damaged containers could not be reconciled solely from the portal record, and the operators combined carrier manifests with recovered markings and diver reports. Cargo owners were notified through their carriers and appointed claims representatives.
The port remained closed to commercial shipping for several months. Services were diverted to other terminals in the network and to competing ports, with additional inland transport and storage arrangements. Recovery work around the wreck constrained the order in which the access channel and turning area could be reopened.
Limited access resumed in November following clearance of a controlled passage and approval by the harbour authority. Restrictions remained on vessel movements, and the affected berth was not returned to service. Assessment of the wreck, damaged cargo and the incoming vessel continued separately from the reopening programme.
Liability position
The port operators, vessel interests and cargo representatives notified claims concerning the loss of the ship and its cargo, collision damage, salvage expenditure and interruption of port operations. The operators alleged that the HAWD connector had introduced instructions into a control environment that the commissioned system was not intended to operate.
HAWD denied liability. Its response referred to the agreed status-reporting scope, the port’s network arrangements and the gateway’s acceptance of messages from the integration host. It disputed whether the bench reconstruction established the complete sequence at the berth and maintained that loading supervision, vessel stability and equipment interlocks remained the responsibility of the relevant operators and suppliers.
The operators relied on the onsite implementation record and the recovered connector in reply. HAWD referred the notifications to its indemnity advisers and supplied the preserved technical material through the appointed representatives. No allocation of responsibility or settlement had been agreed at the report date.
The vessel capsized with approximately £500 million of cargo aboard. The port was blocked for several months and has reopened with restrictions. The direct integration remains disconnected. Recovery and claims assessment continue; HAWD denies liability.