Field report: Hong Kong perimeter replacement

POSTED: 19.09.2019AUTHOR: ADMIN18 MIN READCOMMENTS: 0

Onsite replacement of an obsolete perimeter firewall pair at a client’s Hong Kong office. The engagement followed an unsuccessful installation by a local contractor, during which the new equipment established a working inter-office tunnel but failed to preserve file access between Hong Kong and London.

Engagement and inherited position

The Hong Kong office operated its internet access, remote administration and London connectivity through two appliances which were no longer covered by a supported firmware programme. Replacement hardware had already been procured. A local contractor had staged the new pair, transferred the visible policy configuration and brought up the site-to-site VPN during an agreed maintenance window.

Internet browsing and ordinary reachability tests passed. File sharing did not. London users could no longer open the Hong Kong departmental shares, and Hong Kong staff lost access to several London-hosted working folders. Restoring the old firewall pair immediately restored service. The contractor repeated the change with revised rules, obtained the same result and left the obsolete equipment in production.

The client requested an engineer from Half Assed Web Design to attend in person, establish why apparently equivalent configurations behaved differently and complete the replacement. The agreed deliverables were a working perimeter, validated inter-office access, retirement of the old appliances and a handover record for the London support team.

LOCATIONHong Kong regional office / London central support
SCOPEFirewall pair replacement, VPN commissioning and file-service validation
INITIAL STATEProduction operational on obsolete firewalls; replacement pair disconnected
LOCAL COVEROffice facilities staff and a contracted installation technician
CHANGE CONSTRAINTPreserve existing addressing and user-facing share paths

First attendance — discovery and traffic comparison

The attending engineer arrived with the contractor’s exports, a current logical network diagram and a list of affected share paths. The diagram showed a conventional office LAN behind the edge pair, a virtualisation cluster, departmental file services and a routed connection to London. It did not identify an additional internal security appliance.

Comparison of a successful file session on the old pair with a failed session on the new equipment produced a useful distinction within the first hour. The working connection did not reach the expected destination port. A long-standing translation rule redirected the file-service transport to a non-standard listener behind a shared internal address.

The address represented two different legacy server paths rather than one ordinary file server. One path accepted the conventional CIFS connection; the other carried the working departmental shares through an alternate listener. A combination of service redirection and destination translation made the two appear to occupy the same internal IP. The user-facing paths concealed this arrangement, and an old description field identified both destinations simply as “FILE”.

The local contractor had copied the standard file-sharing rule and the visible address object. This produced a policy which was internally consistent but did not reproduce the alternate transport. The engineer assessed the discrepancy as the principal cause of the previous failed migrations. No change to workstation configuration or share naming was required.

Replacement configuration

The new firewalls were configured with the existing subnets, explicit routes, the documented VPN selectors and a narrowly scoped translation for the alternate file-service path. The relevant traffic was excluded from automatic protocol interpretation where the legacy encapsulation could not be represented accurately by the new inspection profile.

Administrative access was restricted to the agreed support sources. The pair’s own high-availability functions were tested, logging was enabled and the inter-office tunnel was re-established. The engineer recorded the additional translation in the change notes as a legacy compatibility requirement, pending a later file-service consolidation.

The new configuration reproduced the required file access. Test files could be created, opened, renamed and deleted from both offices. Larger transfers completed without interruption, permissions behaved as expected and existing mapped drives reconnected after workstation sign-out. The engineer also checked the client’s accounting front end and a customer-record lookup from a Hong Kong desk.

Acceptance and equipment retirement

The engineer called the London team while the Hong Kong installation remained under observation. Remote engineers confirmed access to the expected shares and management endpoints. A member of the client’s finance team opened a current workbook from London, while Hong Kong staff confirmed that normal business applications were available locally.

A controlled failover between the new appliances completed successfully. After a further observation period, the client accepted the change. There was no outstanding connectivity fault and no visible reason to retain the old pair in the production rack.

Before leaving, the engineer took complete system images of the retired firewalls, including their boot partitions and installed configuration, and placed the files on an encrypted USB stick. The portable copy was intended to be uploaded to the project repository after the return journey. The London team had the ordinary configuration exports but not these full images.

The old appliances were disconnected, stripped of client labels and placed in the building’s electronic-waste collection bin. The collection contractor removed that load before the subsequent incident was understood. The engineer signed out, travelled to the airport and boarded the return flight to London Gatwick with the USB stick in hand baggage.

Return flight — loss of production connectivity

Several hours after acceptance, while the engineer was airborne, the Hong Kong office reported that its network had stopped working. Shared folders disconnected, accounting sessions froze and internal application pages ceased responding. London monitoring recorded widespread loss of reachability rather than the isolated file-service fault seen during the contractor’s earlier attempts.

The engineer could not be contacted during the flight. Calls went unanswered and messages remained undelivered. The full images of the old firewalls existed only on the USB stick travelling with them, and no one in London could inspect the additional services or files contained in those images.

The retired appliances were no longer available for reinstatement. Remote support therefore began with the new firewall logs, the standard exports and assistance from local office staff. The site-to-site tunnel appeared established, but almost all useful destinations beyond it were unreachable.

The remaining accessible host

After several attempts, London established a remote VPN session which could reach one legacy address. The responding machine identified itself as a Windows Server 2003 system. Its name and share list suggested an old departmental file server, although no current application owner could account for its continued operation.

An SSH session could be opened to the address using a retained administrative account. This was unusual for the documented Windows estate. The host ran an ancient SSH service, and the connection behaviour suggested that the endpoint presented to London was not negotiating directly with that service.

No Remote Desktop connection could be established. Ordinary management probes failed, and attempts to reach adjacent systems from the Windows session produced no useful route. Beyond SSH, the only observable service was a restricted file-sharing path. Even that accepted only a limited set of exchanges associated with SMB1, referred to as CIFS 1.0 in the inherited notes.

The team concluded that an undocumented internal firewall probably sat in front of the server. It appeared to terminate the incoming SSH session and relay a separate connection to the older service using a compatibility downgrade. Its policy blocked everything except that relay and a small subset of legacy file-sharing traffic.

Working hypotheses

The limited access prevented a complete topology survey. One theory was that the replacement had exposed a loop in an internal segment which the old pair’s forwarding behaviour had concealed. Another was that a second system behind the shared address performed an undocumented function which the old appliances had been silently offloading.

The Windows Server 2003 host remained the only reliable point of observation. Its event logs showed little recent interactive use, and its visible shares contained an unremarkable collection of old directory structures. Those findings were treated as evidence of a neglected legacy server rather than a deliberate decoy.

London asked Hong Kong staff to locate and photograph switches, routers and firewalls, including equipment outside the main rack. Several small appliances carried old labels which did not correspond to the supplied diagram. Staff could describe indicator lights and cable positions but could not establish the function of every device.

Restart and temporary restoration

Under telephone instruction, local staff restarted the new perimeter pair and the identified core switch. Network access returned. London could once again reach ordinary management addresses, and users began reconnecting to their shares and applications.

The recovery lasted only a few minutes. Switch utilisation rose sharply, packet loss spread across the office and the same services disappeared. The remote VPN connection to the Windows Server 2003 address survived throughout the recurrence.

A second observation of the restart sequence confirmed that the pattern was repeatable. The site operated normally for a short interval after the core switch started, then entered a sustained traffic condition which overwhelmed production communication. The legacy SSH path remained available while the rest of the estate became inaccessible.

The team’s working theory shifted toward a packet storm involving the old server’s CIFS exchanges and the new firewalls’ handling of those exchanges. The server’s exceptional visibility suggested a privileged network position. Its precise relationship to the second backend behind the shared IP remained unclear.

Controlled shutdown for identification

The remote engineers proposed stopping the Windows Server 2003 guest to remove the suspected traffic source and identify which virtual machine it actually was. Hong Kong staff were asked to watch the local virtualisation console and report which guest changed state. A graceful shutdown was selected rather than an immediate power interruption.

The instruction was issued through the remaining SSH session. The Windows host began its normal shutdown sequence and the session closed. Local staff saw the relevant guest disappear from the console, followed almost immediately by management errors affecting other guests.

Within the same interval, the hypervisor console stopped presenting a usable inventory. Core network access failed completely. The previously persistent management path did not return, and the new firewall pair could no longer reach the internal destinations required for recovery.

The shutdown was recorded as the last confirmed administrative action before the loss of the remaining access. At that point the team still had no documentation connecting the guest’s power state with any destructive operation elsewhere in the estate.

Gatwick — receipt of the original system images

The attending engineer’s telephone connected after landing at Gatwick and received the accumulated incident messages. The London team briefed them before they left the terminal. Using airport connectivity, the engineer uploaded the encrypted archive from the USB stick and supplied its access details through the agreed internal channel.

The laboratory mounted the old firewall images for inspection. Unlike the ordinary policy exports, the images contained the custom startup environment, auxiliary daemons, scripts and locally retained logs. These explained several configuration objects which had appeared redundant during the replacement.

The appliances had not been acting solely as perimeter firewalls. They participated in a separate internal control system whose operational state depended on both the edge devices and the continued behaviour of the Windows Server 2003 guest.

Reconstructed security architecture

The second internal firewall was an intrusion tripswitch. An earlier network engineer had designed it to isolate and, under specified conditions, destroy the local environment if remote supervision could no longer establish that the site remained trustworthy.

The apparently normal file-sharing destination on the standard CIFS port was a distraction. It exposed the Windows Server 2003 honeypot, while the alternate listener carried genuine file traffic to the production backend. The unusual dual-server arrangement was therefore part compatibility layer and part security mechanism.

The SSH relay allowed a remote supervisory system to reach the honeypot through its obsolete service without opening ordinary management access to the protected segment. The narrow CIFS policy was intended to make the guest appear credible while limiting the operations available through it. Its accessibility during the wider outage was deliberate.

PERIMETER HEARTBEATCustom agents on the original firewall pair renewed an internal liveness state
REMOTE WITNESSA supervisory connection checked that the honeypot remained reachable and unchanged
CORE SWITCH CONTROLNormal forwarding remained enabled while the required supervisory conditions were satisfied
LOSS OF BOTH HEARTBEATSA deliberate network-flooding condition denied ordinary access to the production estate
HONEYPOT TAMPER EVENTThe internal controller invoked a destructive reset of virtualisation storage and core network systems
ASSUMED RECOVERYRebuild from an independent hourly recovery copy

Why the cutover initially passed

The engineer had correctly reproduced the unusual file-sharing transport. All acceptance tests therefore exercised working production services. What the migration had not reproduced was the custom heartbeat agent and its registration with the internal controller.

The old pair had renewed its supervisory state shortly before disconnection. The controller retained that state for a grace interval, including a deferred remote-witness check, so the new firewalls could pass testing while the internal system still regarded the perimeter as supervised. The last inherited state expired after the engineer had boarded the aircraft.

When both original heartbeat sources remained absent, the controller instructed the core environment to enter its denial condition. The resulting flood was not an accidental layer-two loop. It was the configured response to an assumed loss of perimeter integrity.

Restarting the core switch and edge equipment briefly restored ordinary forwarding while the controller re-established its state. Once the same missing-heartbeat condition was evaluated, the flood resumed. The protected relay to the honeypot remained available because that path was required for the remote witness.

Why the shutdown was destructive

The honeypot was intended to remain powered on and unchanged. Administrative interference, including a shutdown through the management relay, was classified as evidence that an intruder had obtained privileged control. The controller did not distinguish the support team’s graceful shutdown from the hostile action anticipated by its original author.

On receiving that event, the internal firewall used retained management privileges to initiate the destructive recovery sequence. The sequence affected the hypervisor boot environment, attached production datastores and the configuration of the core network systems. Its purpose was to remove an attacker’s ability to continue operating the site, on the assumption that trusted copies existed elsewhere.

The shutdown did not itself corrupt the production data. It supplied the event which caused a different system, with far greater privileges, to erase it. None of that relationship appeared in the guest description or the current support documentation.

The hourly backup assumption

Recovered logs contained references to an hourly recovery process. Initial review raised the possibility that the office could be rebuilt from a recent image after the controller was disabled. Examination of job history removed that option.

The last successful independent copy dated from approximately eleven years earlier, in 2008. A subsequent destination change had left the scheduled task present but unable to complete. Later log entries recorded repeated attempts and failures, not completed backups. No evidence of a current offsite recovery set was found.

The security mechanism did not require a successful backup before permitting destructive action. The continued existence of the schedule was treated as sufficient evidence that recovery provision remained in place. Storage snapshots and local replicas found in the current configuration were within the same management and destruction boundary.

The surviving 2008 material described a materially different business. It could establish some historical configuration and a small number of old records, but it could not recover the present accounting system, customer database or subsequent eleven years of operational activity.

Original deployment file

The client’s archived project file showed that the Hong Kong office had contained two employees when the arrangement was introduced. Its local systems held a limited working set, and the premises had no resident engineer. The original specification placed considerable emphasis on the risk of an overseas compromise continuing unchecked until London could arrange attendance.

The installation had been deliberately over-specified to accommodate anticipated growth. The combination of a remote witness, an internal tripswitch and an hourly rebuild source had been presented as a means of containing a remote incident without waiting for an engineer to reach the site.

By the date of the replacement, Hong Kong had more than 300 employees. It hosted accounting and customer data for the client’s entire East Asian operation. The office had grown into the capacity of the original platform and subsequently expanded it, while the old security control remained attached to the management infrastructure.

No corresponding reassessment had been recorded of the destruction boundary, the controller’s privileges or the business consequences of activating it. The scope of the safeguard had increased with the estate without a documented decision to accept that increase.

Firmware provenance

During image analysis, laboratory staff found an earlier version of the Half Assed Web Design logo in the custom firewall administration interface. The same artwork appeared in a local recovery page beside the supervisory component’s version information.

The build predated the current document repository. No signed design approval or named software maintainer could be located from the surviving package. The logo established an association with an earlier Half Assed delivery environment, but the installation team could not identify an available engineer who would accept authorship of the tripswitch logic.

The provenance finding was added to the incident record. The replacement engineer’s conclusion that the devices contained only ordinary firewall configuration was revised to reflect the contents of the full images.

Second Hong Kong attendance

The engineer was booked onto a further flight to Hong Kong after a brief laboratory handover. On arrival, the internal controller was identified physically and isolated before any additional equipment was started. The affected storage and management systems were then examined with the local technician and the client’s regional operations lead present.

The assessment confirmed that the emergency routine had completed against the production datastores, rather than merely removing virtual-machine registrations from a management screen. Available storage members contained the effects of deliberate erasure. Replicated volumes reflected the same destructive operations, and the local snapshot catalogue was no longer a usable recovery source.

Core switching and firewall service could be reconstructed using new configurations. That work could restore connectivity to the office but could not recreate the erased virtual disks. The images carried back from the first visit contained the retired firewalls’ operating environment, not copies of the accounting and customer data.

London searches found no independent current copy of the regional databases. The inter-office shares had provided access to data hosted in Hong Kong; their successful use from London had not created a second authoritative copy there. The 2008 archive remained the most recent verified independent recovery material.

Final assessment

The initial file-sharing diagnosis was correct but incomplete. It explained the failed local migration without establishing why the legacy arrangement existed or what other functions depended on the retired equipment. Acceptance confirmed present service availability within an unrecognised grace period.

Subsequent remote actions followed a plausible fault-isolation sequence using the only surviving management path. That path led to the device whose alteration was defined as the trigger for destroying the rest of the environment. The controller continued to enforce an eleven-year-old security assumption after its recovery provision had ceased to operate and the site’s business role had changed substantially.

RECOVERY CONCLUSION

The current Hong Kong production estate, including the accounting and customer data hosted for the client’s East Asian operation, is designated a total data loss. The obsolete firewall images explain the incident but contain no recoverable copy of the lost business systems. Network reconstruction and application reinstallation are separate recovery projects; neither changes the data-loss finding.